//Project Management Professional (PMP)® Exam – Practice Question

Project Management Professional (PMP)® Exam – Practice Question

Today’s Question – Q0203

____________analysis helps determine which risks have the most impact on the objective.

A) Sensitivity
B) Risk
C) Reserve
D) Risk Influence

Q0202 – Below is the answer to the previous question:

You are in the middle of managing a project and two of the engineers assigned seem to be having frequent disagreements. You ask them to resolve their differences through a discussion, but this does not yield any results. You decided to meet with them and suggest some changes in the way they work with each other. This still does not resolve the issue, and you find that the project schedule is beginning to suffer. What is your next course of action?

Answer: Take disciplinary action since the needs of the project are not being satisfied

Explanation: After the project manager has tried resolving the matter, it is time to employ more formal conflict resolution mechanisms, such as disciplinary action. PMBOK® Guide 5th edition, Page 283