//Project Management Professional (PMP)® Exam – Practice Question

Project Management Professional (PMP)® Exam – Practice Question

Today’s Question – Q0201
During the execution of your project, you decide that you would like to have charts of your project status cost and schedule, display certain key project data on the wall, and hold your daily project meetings in a specific conference room. Such a place would be called a:

A)  Ground Zero
B)  Battlefield
C)  War Room
D)  Huddle Room

Q0200 – Below is the answer to yesterday’s question:
Upon obtaining the project charter, the Project Manager of a project starts acquiring the project team immediately. Is this correct?

Answer: No. Acquisition of the project team is primarily an Executing Process Group activity.

Explanation: No, the project team is not acquired immediately after signing of the project charter. PMBOK® Guide 5th edition, Page 255

2017-11-09T00:54:05+00:00